4. January 2018

Siemens projects De Warnes and Del Sur – Launch of Installation

Del Sur Eight Exhaust Systems SGT 800 were delivered in time to the both sites Del Sur and De Warnes in time, Roland Nesler the Project Manager said. The 56 sea freight containers were shipped from Cat Lay Port in Vietnam to Arica in Chile. From here the Exhaust Systems were transported on trucks to the both site location.

The assembly & installation on both sites started middle of December 2017. We have a very good progress with the assembly & installation thus we can convert the first gas turbine unit to the new Exhaust System in the second half of February followed with the conversion of the other units every 14 days, Jack Kelly the COMPACT Global site manager said. 